Our tip for the activity sequence:

unload new tracks – detach rail fastenings –
shift new rails – replace sleepers and tracks –
tighten rail fastenings – dispose of old rails –
integrated ballast cleaning / tamping –
1st new ballast supply – filling / profiling –
1st stabilisation – 2nd new ballast supply –
2nd filling / profiling – 2nd stabilisation –
track welding